"Per ARDOT's schedule, they will not be able to even start construction until December 2027, and that's just not acceptable."
City Manager Tyler Richards said that to the Texarkana, Arkansas Board of Directors on July 20, 2026, as Texarkana Today reported. He was talking about the closed Seibert Street bridge. The comment also fits the Arkansas side's road calendar as a whole. The two largest state-run projects carry dates that now sit years out. The street work you can see this fall is the work City Hall has contracted for directly.
The three projects that come up most often show the split clearly.
| Project | Who controls it | Latest status in public records |
|---|---|---|
| Seibert Street bridge | ARDOT grant for replacement; city plans its own demolition and temporary crossing | Closed. A resident asked for an update at the Oct. 5, 2026 board meeting, and coverage reported no new timeline. |
| East 24th, Oak and East 48th Street rehabilitation | City contract with Francis Excavating | Work under way. A change order was approved Oct. 5, 2026. |
| State Line Avenue and Hazel Boulevard reconstruction | ARDOT, partnering with TxDOT | ARDOT's Sept. 25, 2026 staff minutes list a scheduled date of 2030 |
The Bridge the City Plans to Take Down Itself
The Seibert Street bridge goes by Structure No. 19272 in city paperwork. The Board passed a resolution on April 7, 2025, asking ARDOT for federal aid to replace it. The city did get an ARDOT grant for the replacement, a project estimated at about half a million dollars. That money came with an order of steps. ARDOT would not allow demolition or a temporary crossing until a feasibility study was finished. The study is now done, and it found the bridge must be fully replaced.
Even with the study done, the state's construction schedule still points to December 2027. ARDOT also declined to repay the city for tearing down the old structure and building a temporary crossing on its own. Richards told the board in July that the city was raising money to demolish the bridge, haul off the debris and install a temporary crossing itself, using rented equipment. He said he hoped to have a timeline within a couple of weeks.
That July discussion started when an East Side Drive resident asked the board about the closure and told directors the bridge matters for emergency response on that side of the railroad tracks. Close to three months later, at the Oct. 5 meeting, another resident asked for an update on the closed bridge. Texarkana Today's account of that meeting records the request and gives no answer about a demolition date or temporary crossing. At the same meeting, Ward Director Harris asked for a meeting with Union Pacific Railroad about a pedestrian underpass at Seibert Street.
As of the Oct. 5 board meeting, then, the bridge is still closed. The state's replacement can't start before December 2027. The city's quicker fix depends on a funding and equipment plan that has not been made public.
Oak Street Shows What a City Contract Can Do
A short drive away, the city's own street program is moving at a different pace. On July 20, the same night as the bridge update, the board approved a contract with Francis Excavating to rehabilitate East 24th Street, Oak Street and East 48th Street. The low bid was $1,787,729.28, with a not-to-exceed total of $2,144,795.14 once contingency was added. The pre-vote description called for milling, cement stabilization and new asphalt on East 24th Street between Jefferson Avenue and Broad Street.
By Oct. 5, crews had found trouble under the surface. The board approved a $164,154.04 change order for extra milling, cement stabilization and base repair after soft spots turned up on Oak Street. That brought the contract to $1,984,643.32, which Texarkana Today reported is still within the approved budget. Director Harris asked whether the stretch between Preston Street and the railroad tracks would be finished, and Richards said yes.
The Oak Street soft spots went from discovery to an approved fix in a single board meeting, while the contract stayed within its budget.
The city is lining up more work the same way. In July the board also approved engineering contracts with A.L. Franks Engineering to design 2025 street bond projects, including McClure Road, Line Ferry Road, Grand Avenue, East 43rd Street, East 36th Street and Arkansas Boulevard. At the Oct. 5 meeting, the consent agenda included a separate Francis Excavating contract for the County Avenue detention basin and the Bobby Ferguson Park spillway. The board votes on each of these, and the city pays for them.
State Line Avenue Moved From 2028 to 2030 in ARDOT's Own Records
The biggest project on the list is also furthest off, and it has moved further in the past year.
Ahead of an Aug. 21 comment deadline, KTBS reported that ARDOT was taking public comments on rehabilitating State Line Avenue from 7th Street to Arkansas Boulevard, a stretch last reconstructed more than five decades ago. The plan included repaving, sidewalks, rebuilt driveways, better drainage and new traffic signals, plus a rebuild of Hazel Boulevard from 7th Street to State Line. TxDOT is partnering with Arkansas on the job. KTBS said construction was expected to start in 2028. ARDOT's project page for Job 030477 describes the same scope, including signal, drainage, pedestrian and bicycle improvements.
The 2025–2028 Statewide Transportation Improvement Program still lists Job 030477 for federal fiscal year 2028, with $9.9 million shown as Arkansas's share of the partner project. ARDOT's internal staff minutes dated Sept. 25, 2026 list the project as "STIP FFY: 2028" and "SCHEDULED DATE: 2030." The two documents also give different lengths: 2.13 miles in the STIP and 2.46 miles in the minutes. KTBS's coverage used 2.5 miles.
The minutes add details that weren't in the KTBS coverage:
- Design: a reconstruction with a 5-foot sidewalk on the east side and an 8-foot shared-use path with lighting on the west side
- Traffic: 3,500 to 21,000 vehicles a day, depending on the segment
- Work zone: rated "Significant" under ARDOT's work zone policy
- History: first appeared in the 2016–2020 STIP and was programmed on Aug. 4, 2016
- Public input: a public meeting held Aug. 7, 2025 at Beech Street First Baptist Church, 507 Pecan Street
That works out to ten years from programming to the 2026 minutes, and the minutes still put construction four years out. A shared-use path along State Line would give the Arkansas side a walking and biking route on its busiest commercial road. Based on ARDOT's most recent schedule, that path is a 2030-or-later project.
Who Handles Interstate Signage
A smaller request at the Oct. 5 meeting followed the same path. A resident asked the city to restrict loud engine braking by trucks on Interstate 30 between Jefferson Avenue and Fairgrounds Park, where neighborhoods sit on both sides of the highway. Richards said any signage would have to come from the Arkansas Department of Transportation and that staff would put the resident in touch with the district highway representative.
The Seibert Street bridge replacement, State Line Avenue and I-30 signage are all on ARDOT's books. Neighborhood paving, the Grand Avenue and Arkansas Boulevard design work and the Bobby Ferguson Park spillway come before the city board, where public comment has already brought answers on Oak Street and a promise about the Preston Street stretch.
The board's next meeting is at 6 p.m. Monday, Oct. 19, in the board room at City Hall, 216 Walnut St. If the city has a timeline for demolishing the Seibert Street bridge and putting in a temporary crossing, that meeting is where it is most likely to come out.
Road projects change how a street works long before they're finished. They affect which route gets you across the tracks, which stretch of pavement is new, and which corridor will be a work zone once ARDOT's schedule arrives. If you own a home near Seibert Street, Oak Street or State Line Avenue and want to know how this work fits into your plans, Teresa Liepman follows Arkansas-side projects like these as they move through City Hall and ARDOT. Request Your Free Home Valuation, and we'll walk through what's scheduled near your address.